• To protect the electrical cable all cable conduits
are to be fitted with cable sleeves or flexible plas-
tic pipes.
• After successful lift installation and before first
commissioning, the operating company must
have the lift grounding conductors inspected on-
site according to IEC regulation (60364-6-61). An
insulation resistance test is also recommended.
8.2

Setting up the lift

Before setting up the lift, ensure that everything
possible is done to prevent accidents due to
careless assembly. This includes, above all, the use
of safe auxiliary means (e.g. cranes, forklifts and
a sufficient number of people), diverse supports
and a sufficient barrier to prevent unauthorised
access.
• Carefully remove the lift from the wooden crate
and check for damage.
• Position the lift according to the data sheet at the
desired set up location.
• Set up the unit, connect power supply.
i
The set up location of the operating unit can be
selected from two variants. Either in the drive-in
direction at the front right or left.
• Fill with hydraulic oil, the manufacturer recom-
mends a high value hydraulic oil with a viscosity of
32 cst. The required oil volume is approx. 14 litres.
After filling, the oil must be between the marks on
the oil dipstick or approx. 2 cm below the oil filling
supports (11).
11 Oil filling supports
• Move the lifting upwards to approx. 1,500 mm.
• Check the alignment of the base plates again
and anchor the lift. Holes for floor anchoring
74
are to be placed through the holes in the base
plates.
Clean the bore holes by blowing them out with
air. Insert safety anchors into the holes.
The manufacturer recommends using approved
safety anchors and to follow anchor manufactur-
er's instructions.
Before anchoring the lift, check whether the con-
crete is of quality C20/25 up to the finishing level
of the completed floor. In this case, take the an-
chor length from the anchor manufacturer's data
sheet. If there is a floor covering (tiles, screed) on
the weight bearing concrete, the thickness of this
covering must be determined.
• Anchor the unit to the floor.
• Align the lift.
To prevent hollow spaces, correct any uneven-
ness in the floor by putting shims under the base
frame (e.g. thin metal strips). Use suitable supports
to ensure continuous contact between the floor
and base frame.
• Tighten safety anchors with torques recommend-
ed by the manufacturer.
Each anchor must be tightened to the required
!
torque. Safe operation of the lift is not guaran-
teed with a lower torque. Follow the instructions
of the anchor manufacturer.
• Move the lift upwards and downwards several times,
then check the anchors with the torque wrench
and tighten if required. Check the hydraulic lines for
leak-tightness.
• Balance the lift again if required.
• Mount all hose covers.
• Anchor the foot bumpers (optional) included be-
side the lift on the floor. For this, lower the lift to
the lowest position. Position the foot bumpers and
permanently anchor them Distance between the
drive in rails and the foot bumpers approx. 20 mm
(foot bumpers may not touch the drive in rails).
11
002
Position of the foot bumpers (optional)
OPI_JUMBO LIFT 4000 NT_V3.0_DE-EN-FR-ES-IT
016

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Nussbaum jumbo lift 4000 ntNussbaum jumbo lift 4000 nt inground

Table des Matières