ABB IPM/S1.1 Mode D'emploi page 8

Table des Matières

Publicité

Les langues disponibles
  • FR

Les langues disponibles

  • FRANÇAIS, page 10
Installation
1
Strip cable approx. 60 mm.
2
Shorten braided shielding to approx. 10 mm
and pull it back over the cable jacket. Shorten
two pairs of wires (e.g. brown and blue) as
insertion aid by approx. 10 mm more than the
other two pairs of wires.
3
First insert the cable with the longer wires (e.g.
green and orange) vertically into the wire distri-
butor.
4
Swing cable toward the spine and insert cable
so that the spine is seated under cable jacket!
5
Pull the wires into the coloured wire terminals
to fix them. Cut off the projecting wires
6
Insert wire distributor to the stop and lightly
press down.
7
After seating the distributor, insert the moun-
ting wedge from the rear and press in.
8
Swivel strain relief bar onto the cable jacket/
shield and press it on.
9
Tautly fix the cable tie (fastener to the bottom).
10 To disassemble
- Loosen cable tie
8
- Swivel strain relief bar to the top
- Pull out mounting wedge
- Lever up cable distributor with screwdriver
and take it out

Publicité

Table des Matières
loading

Table des Matières