Site Requirements
1. Counter able to support at least 200 pounds (90kg).
2
Counter area large enough for machine.
3. Minimum clearance of 2˝ around machine.
4. Machine must be level within 2˚ for proper operation.
The brewer must be disconnected from the power source until specified in Initial Setup. Refer to Data Plate
on the Brewer, and local/national electrical codes to determine circuit requirements.
Electrical Hook-Up
CAUTION: Improper electrical installation will damage electronic components.
1. An electrician must provide electrical service as specified.
2. Using a voltmeter, check the voltage and color coding of each conductor at the electrical source.
3. Connect the dispenser to the power source.
4. If plumbing is to be hooked up later be sure the dispenser is disconnected from the power source. If
plumbing has been hooked up, the dispenser is ready for Initial Fill & Heat.
120/208 & 120/240V AC
Single phase models
120V
Models

ELECTRICAL HOOKUP

FOR INDOOR USE ONLY
WARNING
120 / 208-240 volt ac models
NOTE: This electrical service requires 3 current carrying conductors
(Neutral, L1 and L2) and a separate conductor for earth ground.
NOTE: This electrical service consists of 2 current carrying conductors
(L1 and Neutral) and a separate conductor for chassis ground.