Electrical Connections; Loose / Broken Cable Switch; Commissioning The Platform - Nussbaum ATT COMBI LIFT CL 4.40 S Manuel D'exploitation

Table des Matières

Publicité

Les langues disponibles
  • FR

Les langues disponibles

Clean the bore holes by blowing them out with
air. Insert safety anchors into the holes (also see
4.4 Selecting anchor).
1
2
Anchoring
1
Column
2
Base plate
3
Positioning the fastening anchor
• Before anchoring the lift, check whether the
concrete is of quality c20/25 up to the finishing
level of the completed floor. In this case, take the
anchor length from the anchor manufacturer's
data sheet.
If there is a floor covering (tiles, screed) on the
weight bearing concrete, the thickness of this co-
vering must be determined. Afterwards, take the
anchor length from the anchor manufacturer's
data sheet.
• The base plates (2) are also to be supported with
suitable underlays (thin metal strips) to ensure
precise vertical set up and contact between the
base plate and the floor.
• Tighten the anchors using a torque wrench.
Each anchor must be able to be tighte-
ned to the torque specified by the ma-
nufacturer. Safe operation of the lift is
not guaranteed with a lower torque.
• Tighten anchors with the curved washer to the
required torque, until the washer is laying flat
against the base plate (2). This ensures a secure
anchor connection.
50
COMBI LIFT 4.40 S-S A-S PLUS-S PLUS AMS - HYMAX II 4000 S-S A-S PLUS-S PLUS AMS
3
002
4.7

Electrical connections

• Provide an on-site electrical connection of 3 ~/N
+ PE, 400 V, 50 Hz, fuses with 16 A, slow-blow (also
see Section 15 Electrical circuit diagram).
• Have an electrician connect the electric cable
to the customer-provided mains breaker (e.g. a
Cekon plug).
4.8

Loose / broken cable switch

The loose / broken cable switch (4) is
only pre-mounted at the factory! After
threading in and fastening the cable,
the switch must be set accordingly.
This is required again after each cable
change or after the platform has been
moved.
4
5
4
Loose / broken cable switch
5
moving trigger element
6
Cable holder
4.9

Commissioning the platform

• Tighten screws on the beams.
• Refill hydraulic oil The total oil volume of the oil
tank is approx. 13 litres.
• Lift the platform slightly by pushing the "LIFT"
button o (8) and at the same time pushing the
"bridge" button (11).
• Remove assembly stands and place the plat-
form into the safety ratchets.
003
6
004
25.09.2015
20110006 OPI

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Att combi lift cl 4.40 s aAtt combi lift cl 4.40 s plusAtt combi lift cl 4.40 s plus amsAtt hymax ii 4000 sAtt hymax ii 4000 s aAtt hymax ii 4000 s plus ... Afficher tout

Table des Matières