Preparation of Piping

Main cause of gas leakage is defect in flaring work. Carry out correct flaring work in the following procedure.
1) Cut the pipes and the cable.
I Use the accessory piping kit or the pipes purchased
locally.
I Measure the distance between the indoor and the
outdoor unit.
I Cut the pipes a little longer than measured distance.
I Cut the cable 1.5m longer than the pipe length.
2) Burrs removal
I Completely remove all burrs from the cut cross section
of pipe/tube.
I Put the end of the copper tube/pipe to downward
direction as you remove burrs in order to avoid to let
burrs drop in the tubing.

3) Flaring work

I Carry out flaring work using flaring tool as shown right.
Indoor unit
[kW(Btu/h]
Gas
<5.6(19,100)
12.7(1/2)
<16.0(54,600) 15.88(5/8)
<22.4(76,400) 9.52(3/4)
Firmly hold copper tube in a bar(or die) as indicated
dimension in the table above.
4) Check
I Compare the flared work with figure right.
I If flare is noted to be defective, cut off the flared section
and do flaring work again.
20
Outdoor Unit
Unit : mm(inch)
Pipe
" A "
Liquid
Gas
1.6~1.8
6.35(1/4)
(0.63~0.71) (0.43~0.51)
1.6~1.8
9.52(3/8)
(0.63~0.71) (0.59~0.67)
1.9~2.1
9.52(3/8)
(0.75~0.83) (0.59~0.67)
Copper
tube
Point down
Bar
Liquid
1.1~1.3
Copper pipe
1.5~1.7
1.5~1.7
Smooth all round
Even length
all round
Slanted Uneven Rough
90°
Pipe
Reamer
Handle
Bar
"A"
Clamp handle
Red arrow mark
Inside is shining without scratches.
= Improper flaring =
Inclined
Surface
Cracked Uneven
damaged
Yoke
Cone
thickness