INSTALLATION

Commissioning

Installation with offset tiles
20
2
1
1 Minimum contact area of the appliance
2 Maximum tile offset
f Adjust the wall clearance. Lock the back panel in place using
f
the fixing toggle (turn 90° clockwise).
11. Commissioning
WARNING Electrocution
Commissioning must only be carried out by a qualified
contractor in accordance with safety regulations.

11.1 Initial start-up

≥ 60 s
f Open and close all connected draw-off valves several times,
f
until all air has been purged from the pipework and the
appliance.
f Carry out a tightness check.
f
f Activate the safety pressure limiter at flow pressure by firmly
f
pressing in the reset button (the appliance is delivered with
the safety pressure limiter deactivated).
f Fit the appliance cover; it should audibly click into place.
f
Check that the appliance cover is seated correctly.
f Secure the appliance cover with the screw.
f
www.stiebel-eltron.com
f Switch the power supply ON.
f
f Check the appliance function.
f
f Remove the protective foil from the appliance cover fascia.
f
Appliance handover
f Explain the appliance function to users and familiarise them
f
with how it works.
f Make the user aware of potential dangers, especially the risk
f
of scalding.
f Hand over these instructions.
f

11.2 Recommissioning

Material losses
!
To ensure that the bare wire heating system is not dam-
aged following an interruption to the water supply, the
appliance must be restarted by taking the following steps.
f Disconnect the appliance from the power supply by
f
removing the fuses/tripping the MCBs.
f Open the tap for one minute until the appliance and
f
its upstream cold water inlet line are free of air.
f Switch the mains power back on again.
f

12. Appliance shutdown

f Isolate all poles of the appliance from the power supply.
f
f Drain the appliance (see chapter "Installation / Maintenance /
f
Draining the appliance").
HDB-E Si |