Fill the hole with earth around the concrete block.
Remove the nuts and washers from the bolts.
Insert the electric cables into the tubes so that they protrude by about 600 mm.
Preparing the barrier
Remove the screws from the dome cover, insert the key in the lock and turn it anti-clockwise.
Lift up the dome cover and remove the inspection hatch .
⚠ Caution! The barrier is set up for installing on the left.
If it is installed on the right, invert the boom opening direction, following the procedure below:
- remove the rod from the transmission arm ;
- release the gearmotor using the key;
- turn the transmission arm ;
- lock the motor again;
- fasten the rod to the opposite hole in the arm ;
- invert the motor phases M and N.
Left
Right
N
M
4
1
3
2