Assembly

5.1

Installation position

With regard to the installation position, pay attention to the flow direction arrow. Installation is only
permitted in the flow direction. When installing the valve in a horizontal pipeline a vertical position of the
spindle is recommended (hand lever at the top) or an inclination of up to 65° from the vertical.
5.2
Notes regarding the installation
Use suitable tools.
Allen keys of sizes 6, 8, 10, 14, 19;
Open-ended spanners;
Torque wrench;
TIG welding machine;
Oxy-fuel welding machine;
Clean tools before the installation.
Use suitable transport and lifting equipment for the installation.
Open the packaging only directly before the installation. Freedom from oil and grease for oxygen
(O
)
2
Valves for oxygen are permanently marked with "O
Only install the valve if the maximum operating pressure and usage conditions of the plant
correspond to the marking on the valve.
Remove protective caps or covers before assembly.
Inspect the valve for dirt and damage.
DO NOT install a damaged or dirty valve.
Avoid damaging the connections.
The sealing surfaces must remain clean and intact.
Seal the valve with suitable seals.
No sealant (sealing tape, liquid sealing tape) may enter the valve.
Respect the suitability for use with O
Connect pipelines in a force-free and torque-free manner.
Stress-free installation.
In order to ensure trouble-free operation, no impermissible static, thermal or dynamic stresses
may be transmitted to the valve. Observe reaction forces.
Temperature-dependent changes in length in the pipework system must be compensated with
expansion joints.
The valve is supported by the pipework system.
The valve must be protected against dirt and damage during construction work.
Remove the transport lock if fitted.
Check the leak-tightness.
5.3
Welding / soldering
Welding / soldering of the valves and any heat treatment that may be required are the responsibility of the
contracting construction company or operating company.
Before welding / soldering
Operating instructions
.
2
herose.com
".
2
Loosen the bolts
Direction of rotation: counter
clockwise
Remove the bolts
Remove the side parts