CAUTION
The position of the electrode is essential for the correct
detection of current ionization.
4.3.4
Final operations
After having cleaned the heat exchanger and the burner:
– remove any carbon residue using a vacuum cleaner
– check that the gasket and the insulation of the front panel (4)
of the combustion chamber are integral. If this is not the case
then replace it
– refit the panel (4) secure it with fastening screws.
5
3
4
4.4
Checks
4.4.1
Checking the smoke duct
It is recommended that the user checks that the smoke outlet
duct is integral and airtight.
4.4.2
Checking the expansion vessel pressure
It is recommended that the expansion vessel on the water side
is drained and that the prefilling pressure is not less than 1 bar .
If this is not the case, pressurize it to the correct value (see
section "Expansion vessel").
Once the checks described above have been completed:
– refill the boiler as described in section "REFILL operations"
– start the boiler up and carry out a smoke analysis and/or
measure the combustion efficiency
– refit the front panel securing it with the two screws which
were removed previously
56
4.5
Unscheduled maintenance
If replacing the electronic board , the user MUST set the
parameters as indicated in the table and in the sequence shown.
Type
No.
tS
0.1
tS
0.2
Fig. 41
tS
0.3
tS
0.4
To enter "Parameter setting and display"refer to the indications
provided in the specific section.
Once the parameters in the table have been set, you must carry
out the "Automatic calibration procedure".
If the gas valve and/or the ignition/detection electrode , are
replaced, the user must still carry out the entire phase of "
Automatic calibration procedure" described in the specific
section.
4.6
Malfunction codes and possible solutions
LIST OF MALFUNCTION/FAULT ALARMS
Type
No.
Fault
AL
01
Smoke thermostat
6
Low water pressure
AL
02
in system
Domestic hot water
sensor fault (return
AL
04
sensor fault for T
models)
AL
05
Delivery sensor fault
Fig. 42
AL
06
No flame detection
Sensor or safety
AL
07
thermostat
intervenes
Fault in the flame
AL
08
detection circuit
No water circulating
AL
09
in the system
Description
Index showing boiler power in kW
0 = 24
Hydraulic configuration
0 = rapid
1 = storage tank with thermostat or
heating only
2 = hot water tank with sensor
3 = bithermic
4=instant with solar power input
Gas Type Configuration
0 = G20; 1 = G31
Combustion configuration
0 = sealed chamber with combustion
control
1 = open chamber with smoke
thermostat
2 = low NOx
Solution
- Contact the Technical
Assistance Centre
- Restore pressure
- Check for any leaks in the
system
- Check connections
- Check the sensor is working
- Check connections
- Check the sensor is working
- Check the integrity of the
electrode and check that it is
not grounded
- Check gas availability and
pressure
- Check the integrity of the gas
valve and the card
- Check the sensor or
thermostat connections
- Deaerate the system
- Check the bleed valve
- Replace the sensor or the
thermostat
- Check that the pump impeller
is not blocked
- Check the integrity of the
electrode and check that it is
not grounded
- Check the integrity of the gas
valve and the card
- Check the rotation of the pump
rotor
- Check the electrical
connections
- Replace the pump
EN
IT
Setting
0
0
0 or 1
1

Publicité