EARTHING THE DEVICE; SEE FIGURE 2
1. Place the strain relief clip (A) about 10-12cm from the eye of the earth cable (B).
2. Slide the eye of the earth cable (B) over the earth pin (C) that is fastened to the housing (D).
3. Slide the first spring washer (E1) over the earth pin (C).
4. Place the hexagonal nut (F) on the earth pin and tighten it.
5. Slide the second spring washer (E2) over the earth pin (C).
6. Slide the strain relief clip (A) over the earth pin (C).
7. Place the last lock nut (G) on the earth pin (C) and tighten it carefully with a spanner #8.
8. Ensure that the sequence follows precisely that shown in figure 2.
INSTALLATION OF THE DEVICE; SEE FIGURE 3/4
The device must be placed in a dry, well-ventilated area and in such a way as to prevent exposure to direct sunlight.
Never place the device immediately after the PH controller and/or salt electrolysis. The best location is – if possible –
after the filter. It must always be installed in the vertical position. The electronic ballast (T) must remain visible so the
UV-C lamp replacement indicator can be seen. Also consider accessibility in connection with maintenance (see also
Maintenance and disassembly).
VENTURI UNIT (SEE FIGURE 3/4)
1. Screw the pressure gauge (H) onto the venture unit hand-tight. Use Teflon tape (not included).
2. Glue the venture unit into the PVC piping using the supplied glue coupling (T), before or at the device's inlet.
Keep in mind that the venture unit must be installed horizontally.
3. Take the hose with the non-return valve (J). Attach the long section of the hose to the air valve (K) at the
bottom of the device. Attach the short section of the hose on the hose nipple (L) of the venture unit.
DEVICE (SEE FIGURE 3/4)
1. Unscrew the lock nut (M) from the housing (D) and save it for attachment of the connection coupling (N)
in step 7.
2. Carefully remove the UV-C lamp (O) from its packaging and insert it into the quartz sleeve (P).
3. Insert the UV-C lamp (O) into the lamp holder (L) and then push the assembly further into the quartz sleeve (P).
Also always ensure that the O-rings (Q1 & Q2) are positioned correctly.
4. Screw the nut (R) back onto the housing (D) hand-tight.
5. Install the pipe clamps (S) at the desired location. This is where the device will be mounted.
(Keep the length of the cables in mind when selecting this location; see also step 6).
6. Mount the electronic ballast (T) at the desired location. (Keep the length of the cables in mind).
7. Use the lock nut (M) to screw the connection coupling (N) onto the housing (D), and ensure that the O-rings (U)
are positioned properly.
8. Place the device in the pipe clamps (S) and glue the connection coupling (N) to the piping and/or the
venture unit.
9. Ensure that enough water is flowing through the device, and then plug the plug into the designated socket.
All the lights on the electronic ballast (T) will light up, after which the green light will remain on. The transparent
connectors (N) enable you to see whether the UV-C lamp (O) is on. Also check everything for leaks.
10. Once the entire system is leak-free, the amount of ozone can be adjusted by means of the ball valve (V) on the
venture unit. The ideal water pressure on the pressure gauge (H) is 0.4 to 0.7 bar.
11. The device can be switched off by simply unplugging the plug from the socket. The electronic ballast remembers