Preparing for
Installation
The following five steps generally apply to all transfer switch installations. The transfer
switch may be installed on either side of the load center.
1. Turn off the main circuit breaker in the load center to ensure your
safety.
Danger: All current-carrying parts on the LINE side of the main
are still live
2. Remove the cover of the load
center.
3. Locate and remove a knockout (ko)
in the bottom of the load center
(Figure 2). Use a 3/4" ko for 6-circuit
models, and a 1" ko for 10-circuit
models.
4. Insert the wires extending from the
end of the flexible conduit through
the ko. Attach the conduit connector
securely with the locknut provided.
5. Anchor the transfer switch to the
wall using the top bracket and
bottom mounting holes located in the
cabinet
behind
compartment cover. Do not attempt
to bend the flexible conduit beyond
its structural capabilities
Wiring the Reliance Transfer Switch to the Load Center
Determine which circuits will be used during an emergency. The residential wattage
requirement chart on the inside front cover of this manual may be used as a guide, but
actual appliance wattages may vary. If a selected circuit is part of a multi-wire branch
circuit, ensure the other branch circuit that shares the neutral is also connected to the
transfer switch. The two circuits must be connected to opposing legs (phases) of the
generator power and a handle tie must be installed on the switch handles so that both legs
are transferred at the same time.

Installation Instructions

You will need the following items:
Electric drill
Screwdriver
Wire cutters/stripper
Hammer
Four anchors and screws
6 or 10 yellow wire connectors (depending on the model)
4 red wire connectors for the 20A and 30A hard-wire models