NOTE:
Cards should be installed in the system, starting with the Card priority, then the slot priority. The first open slot priority should be
used.
Low profile (LP), Half-Height cards can only be installed in Slot 6.
Slots 4, 5, 7, 8 require that CPU2 be installed in the system.
Any cards > 75 W require one or more external power cables to install (power cables are included in base system BOM).
Graphics cards are of equal priority to each other. For multiple GPU card configs, cards must be matched (all same model).
Nvidia GPU's using SLI must reside in slots 4 and 7 with a 2nd processor installed. An SLI cable must also be installed.
Zoom4 - Dual Zoom4 requires dual microprocessor, and both Zoom cards must be populated on CPU2 (slots 4 & 8).
No Teradici P25 or P45 in slot 3