6 Commissioning

6
Commissioning
NOTICE
ALWAYS operate the unit with thermistors and/or pressure
sensors/switches. If NOT, burning of the compressor might
be the result.
NOTICE
Make sure both air purge valves (one on the magnetic filter
and one on the backup heater) are open.
All automatic air purge valves must remain open after
commissioning.
INFORMATION
Protective functions – "Installer-on-site mode". The
software is equipped with protective functions, such as
room antifrost. The unit automatically runs these functions
when necessary.
During installation or service this behaviour is undesired.
Therefore, the protective functions can be disabled:
▪ At first power-on: The protective functions are
disabled by default. After 12 h they will be automatically
enabled.
▪ Afterwards: An installer can manually disable the
protective
functions
protections=Yes. After his work is done, he can
enable the protective functions by setting [9.G]:
Disable protections=No.
6.1

Checklist before commissioning

After the installation of the unit, first check the items listed below.
Once all checks are fulfilled, the unit must be closed. Power-up the
unit after it is closed.
You read the complete installation instructions, as
described in the installer reference guide.
The indoor unit is properly mounted.
The outdoor unit is properly mounted.
The following field wiring has been carried out according
to this document and the applicable legislation:
▪ Between the local supply panel and the outdoor unit
▪ Between indoor unit and outdoor unit
▪ Between the local supply panel and the indoor unit
▪ Between the indoor unit and the valves (if applicable)
▪ Between the indoor unit and the room thermostat (if
applicable)
▪ Between the indoor unit and the domestic hot water
tank (if applicable)
The system is properly earthed and the earth terminals
are tightened.
The fuses or locally installed protection devices are
installed according to this document, and have NOT been
bypassed.
The power supply voltage matches the voltage on the
identification label of the unit.
There are NO loose connections or damaged electrical
components in the switch box.
Installation manual
22
by
setting
[9.G]:
Disable
There are NO damaged components or squeezed
pipes on the inside of the indoor and outdoor units.
Backup heater circuit breaker F1B (field supply) is
turned ON.
Only for tanks with built-in booster heater:
Booster heater circuit breaker F2B (field supply) is
turned ON.
The correct pipe size is installed and the pipes are
properly insulated.
There is NO water leak inside the indoor unit.
The shut-off valves are properly installed and fully open.
The automatic air purge valves are open.
The pressure relief valve purges water when opened.
Clean water must come out.
The minimum water volume is guaranteed in all
conditions. See "To check the water volume and flow rate"
in
"3.2 Preparing water
(if applicable) The domestic hot water tank is filled
completely.
6.2

Checklist during commissioning

The minimum flow rate during backup heater/defrost
operation is guaranteed in all conditions. See "To check
the water volume and flow rate" in
piping" [ 4  5].

To perform an air purge.

To perform a test run.
To perform an actuator test run.
Underfloor screed dryout function
The underfloor screed dryout function is started (if
necessary).
6.2.1

To check the minimum flow rate

1 Check the hydraulic configuration to find out which
space heating loops can be closed by mechanical,
electronic, or other valves.
2 Close all space heating loops that can be closed.
3 Start the pump test run (see
test
run" [ 4  23]).
(a)
4 Read out the flow rate
and modify the bypass valve
setting to reach the minimum required flow rate + 2 l/
min.
(a)
During pump test run, the unit can operate below the minimum
required flow rate.
Minimum required flow rate
20 l/min
6.2.2
To perform an air purge
Conditions: Make sure all operation is disabled. Go to [C]:
Operation and turn off Room, Space heating/cooling and Tank
operation.
piping" [ 4  5].
"3.2  Preparing water
"To perform an actuator
EABH/X16DF6V+9W
Daikin Altherma 3 H W
4P644479-1 – 2020.12