Charging water

1
Connect the water supply to a drain and fill valve (see "Main
components" on page 10).
2
Make sure the automatic air purge valve is open (at least 2
turns).
3
Fill with water until the manometer indicates a pressure of
approximately 29 psi (2.0 bar). Remove air in the circuit as much
as possible using the air purge valves. Air present in the water
circuit might cause malfunctioning of the backup heater.
4
Check that the backup heater vessel is filled with water by
opening the pressure relief valve. Water must flow out of the
valve.
NOTE
During filling, it might not be possible to remove all
air in the system. Remaining air will be removed
through the automatic air purge valves during first
operating hours of the system. Additional filling
with water afterwards might be required.
The water pressure indicated on the manometer
will vary depending on the water temperature
(higher pressure at higher water temperature).
However, at all times water pressure should
remain above 4.3 psi (0.3 bar) to avoid air
entering the circuit.
The unit might dispose some excessive water
through the pressure relief valve.
Water quality must be according to "Safe Drinking
water Act (42 U.S.C. 300f)".

Piping insulation

The complete water circuit, inclusive all piping, must be insulated to
prevent condensation during cooling operation and reduction of the
cooling and heating capacity.
If the temperature is higher than 86°F (30°C) and the humidity is
higher than RH 80%, then the thickness of the sealing materials
should be at least 0.79 inch (20 mm) in order to avoid condensation
on the surface of the sealing.
Installation manual
16

Field wiring

WARNING
A main switch or other means for disconnection,
having a contact separation in all poles, must be
incorporated in the fixed wiring in accordance with
relevant local laws and regulations.
Switch off the power supply before making any
connections.
Use only copper wires.
Never squeeze bundled cables and make sure that it
does not come in contact with the piping and sharp
edges.
Make sure no external pressure is applied to the
terminal connections.
All field wiring and components must be installed by a
licensed electrician and must comply with relevant
local laws and regulations.
The field wiring must be carried out in accordance
with the wiring diagram supplied with the unit and the
instructions given below.
Be sure to use a dedicated power supply. Never use a
power supply shared by another appliance.
Be sure to establish an ground. Do not ground the unit
to a utility pipe, surge absorber, or telephone ground.
Incomplete ground may cause electrical shock.
Be sure to install an ground fault circuit interrupter
(30 mA) in accordance with relevant local laws and
regulations. Failure to do so may cause electrical
shock or fire.
Be sure to install the required fuses or circuit
breakers.
Indoor unit for air to water heat pump system
EKHBH/X054BA
4PW54216-1

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Ekhbx054baEkhbh030baEkhbx030ba

Table des Matières