Support three-phase equipment
Step 1: Check the following requirements before commissioning:
 Correct wire connection
 Ensure all breakers in Line wires at load side are open and each neutral wires of each unit are connected.
Step 2: Turn on all units and configure LCD program 28 as P1, P2 and P3 sequentially. And then shut down all
units.
NOET: It's necessary to turn off switch when setting LCD program. Otherwise, the setting cannot be
programmed.
Step 3: Turn on all units sequentially.
LCD display in L1-phase unit
Step 4: Switch on all AC breakers of Line wires in AC input. If AC connection is detected and three phases
matched with the setting in the unit, they will work normally. If the sequences do not match, it won't
work in Line mode. You must exchange the wires of P2 & P3 or exchange the setting of P2 & P3.
LCD display in L1-phase unit
Step 5: If there is no more fault alarm, the system to support 3-phase equipment is completely installed.
Step 6: Please switch on all breakers of Line wires at load side. This system will start to provide power to the
load.
Note 1: To avoid overload occurring, before turning on breakers in load side, it's better to have whole system in
operation first.
Note 2: Transfer time for this operation exists. Power interruption may happen to critical devices which cannot
bear transfer time.
48
INFOSEC UPS SYSTEM - 15, rue du Moulin - 44880 Sautron - FRANCE - www.infosec-ups.com
Hot Line – Tel + 33 (0)2 40 76 15 82 - Fax + 33 (0)240 94 29 51 - hotline@infosec.fr – 08 17 AA 59 201 05
LCD display in L2-phase unit
LCD display in L2-phase unit
LCD display in L3-phase unit
LCD display in L3-phase unit

Publicité

Chapitres

Table des Matières
loading

Table des Matières