5. Installing the R-Converter Unit (mm)

Parts to procure locally
Suspension bolts or anchor bolts : W3/8 (M10)
Nut : W3/8 (M10)
Washer : W3/8 (M10)
Installing the unit in a ceiling
(1) Install the suspension bolts.
(2) Install the R-Converter unit.
Installing the unit on a wall
(1) Install the anchor bolts.
(2) Install the R-Converter unit.
Do not install the refrigerant pipes on top of the unit
when installing the unit on a wall, otherwise
condensation can enter the electrical devices,
which can cause an electric shock or a fire.
6
Suspension bolt
Nuts
Washer (procure locally)
Unit
Washer (procure locally)
Nut (procure locally)
VIEW "A"
Anchor bolt pitch
Wooden structures
Use tie beams (single storied houses) or second floor beams (two
story houses) as reinforcing members.
Wooden beams for suspending air conditioners must be sturdy and
their sides must be at least 6 cm long if the beams are separated
by not more than 90 cm. The size of the suspension bolts should
be M10 (W3/8). (The bolts are not supplied with the unit.)
A Ceiling
B Rafter
C Beam
D Roof beam
B* Suspension bolt pitch
Ferro-concrete structures
Secure the suspension bolts using the method shown, or use steel or
wooden hangers, etc. to install the suspension bolts.
E Use inserts rated at 100-150 kg each (procure locally)
F Suspension bolts M10 (W3/8) (procure locally)
G Steel reinforcing rod
Ensure that this face is always installed
upwards.
Suspension bolt pitch
Suspension bolt
MIN. 200
Install the R-Converter
unit horizontally.
Obstructions
Anchor bolt
MIN. 500
SERVICE SPACE
MIN. 200
Wall
Washer
(procure locally)
Nuts
(procure locally)