Prior to the application of power to your relay cabinet, all of the following steps
must have been successfully executed.
Inspect each relay load wiring for incomplete termination
Inspect each relay's load wiring for terminals not completely tightened
With each relay in the "OFF" position, check for voltage between the Line & Load
terminals; there should be none.
Inspect all low voltage wiring and ensure that it is complete.
Inspect control power wiring, ensure that it is complete.
Confirm that any unused supply wires on the control power transformer have been
suitably capped.
Confirm that all connected load wiring between the relay panel and it's load has
been completed.
Confirm that wiring between the cabinet and all low voltage devices has been
completed.
Apply power to the cabinet.
Confirm that the cabinet boots properly and returns to the status "normal" screen.
Set the Time & Date from the menu.
Update system software with the latest available software from the website, if
appropriate.
Proceed to panel programming.