Installing A Combustion Air Intake; Electrical Connection; First Ignition; Pellet Loading Procedure - ZANTIA ITACA Manuel D'utilisation Et D'entretien

Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

Closing flange
Stainless steel or
aluminium airtight
closing flange
2.5.11

INSTALLING A COMBUSTION AIR INTAKE

The combustion air intake must be realised ac-
cording to standard UNI 10683.
IMPORTANT: This appliance cannot be used in the event
of shared flues.
2.6

ELECTRICAL CONNECTION

EN
EN
Ensure that the electrical system and sockets can withstand
the maximum power consumption of the product, shown on
the identification plate.
• Ensure that the system is earthed and
equipped with a residual current device, in
compliance with the standards in force
The boiler must be connected to a standard electric sock-
et, 230v – 50Hz voltage, without using adapters, multiple
sockets or extension cables.
Ensure that the mains connection cable is not in contact
with the hot parts of the boiler and that it is not crushed
by it.
The boiler system is protected by a fuse inserted in the
master switch at the rear of the product.
Always remember to unplug the product before perform-
ing any maintenance and/or checks and whenever a long
idle period is foreseen.
fig. 14 electric connection of the boiler
36
External air intake
with non-lockable
grille
Inspection
fig. 13 external flue
Once the power cable at the back of the boiler is plugged in,
move the switch, also located at the back, to (I) therefore:
The switch at the back of the boiler is to power the system.
There is a fuse box at the back of the boiler near the power
socket. Open the lid of the fuse box with a screwdriver and
have an authorised technician change any fuses if neces-
sary (3.15 A delayed).
Socket
3

FIRST IGNITION

ry to have specialised personnel perform the "FIRST
IGNITION" and calibration. To this end, we recom-
mend contacting the authorised Zantia technical
assistance centre. The company shall not be held
liable for malfunctions caused by improper installation, failed or
improper first ignition or misuse. Ensure that the electrical con-
nections and the hydraulic ones (if any) have been made in a
workmanlike manner. Moreover, check that the hydraulic sys-
tem (on the thermo-stoves and boilers) has an adequate expan-
sion vessel to ensure maximum safety. Remember that expan-
sion is calculated by considering 6% of the entire volume
contained in the system.
Any damage related to the system or appliance
shall not be covered by the warranty. A vessel
assembled on the appliance does not ensure ad-
equate protection against thermal expansion sus-
tained by the system's water.
Fill the system by means of a refill valve (to be provided external-
ly to the stove). During the refilling phase, you are advised not to
exceed the maximum pressure of 1 bar. Pressure reading can be
carried out directly from the pressure gauge. The water loading
phase must be carried out simultaneously with the output of air.
Before switching the product on, always check that the
brazier is pushed to the back of the rear wall of the com-
bustion chamber. When the tank is loaded the first time, the
auger must fill up for a certain amount of time during which
the pellets are not dispensed into the brazier.
3.1

PELLET LOADING PROCEDURE

Fuel is loaded by opening the door at the top of the boiler.
Pour the pellets slowly until they deposit at the bottom of
the tank.
Never remove the protective grid inside the
tank. Do not allow the pellet bag to come into
contact with hot surfaces while loading.
Do not insert any other type of fuel in the tank except pellets
compliant with the specifications shown previously.
Store spare fuel a safety distance away from the stove.
translated from the original text
fig. 15 electric power supply
Before commissioning the product, it is mandato-
Installation
Stove switch
Fuse box
Mod. ITACA-TROIA rev 01

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Troia

Table des Matières