§5.4 - General remarks
The torque fastenings of all bolts should be checked after
completion of the compulsory static and dynamic weight
tests at the end of the fitting process, and retightened if
required.
Ensure that all freshly made chassis perfora-
tions are properly deburred, and that all metal
work (cutting, drilling, welding, grinding,...) is
properly treated with an anti-corrosive protection
(e.g. Zinc-spray or Dinitrol). Allow to dry. Con-
sult the FITTING AND BODY BUILDING IN-
STRUCTIONS of the vehicle manufacturer to
take into account their instructions.
M
6) MOUNTING THE PLATFORM & FINALIZING THE MECHANI-
CAL WORK
§6.1 - Mounting the platform to the lift arms
E
Mount the electric controls at this stage [see chapter 7], or at
least to connect the battery and earth cables of the HTL to an
external battery. This will help you to manipulate the hydraulic
cylinders, and to proceed in the mounting of the platform.
M
Grease the 2 articulations where the lift cylinders con-
nect to the lift arms, and the 2 articulations of the tilt
cylinders prior to mounting pins. [See Fig. 6.1]
DHOLLANDIA
6.1
31
1L + 1R