3.Use 
Always install the Foamatic unit in frost‐free rooms only. 
The unit is delivered complete and ready for mounting on a wall or a suitable rack. The unit is 
mounted on the enclosed wall bracket according to description in the installation guide. It is very 
important that all pipe connections are thoroughly rinsed before installation. 
It is very important to use correct nozzle sizes where foam, desinfection or rinsing is carried out. 
E.g. the foam volume produced by the injectors must comply with the nozzle volume. If the 
injectors produce 150 l/min, and three valves for one zone are used, the amount of litres on the 
three valves must also be approx 150 l. If this is not observed, the quality of the foam will not be 
satisfactory. – For further information do not hesitate to contact Ecolabs service department. 
4.Service 
Only authorised and qualified personnel is allowed to carry out service on the unit. Only carry 
out service when the Foamatic unit is disconnected and depressurised. 
1. Disconnect the power supply 
2. Shut of the water supply 
3. In order to depressurise the outlet side ‐ open an external valve. 
The unit is built in sections, which makes it possible to do service on a separate section. However, 
the Foamatic unit is not operational without this section. One section for water and one section 
for each detergent. 
4.1 Components 
4.1.1 Master controller 
Maintenance free.
In case of defects: please contact service technician.
4.1.2 ACC‐01 
Maintenance free.
In case of defects: exchange unit.
4.1.3 Non‐return valve, water 
Maintenance free.
I case of defects, exchange non-return valve.
4.1.4 Non‐return valve, detergents  
Maintenance free.
In case of defects, exchange non-return valve.
4.1.5 Non‐return valve, air 
Maintenance free
In case of defects, exchange non-return valve.