1.
Prepare Site
Flooring
NOTICE: Adequate floor support must be provided. Consult the roughing-in
information packed with the bath for specific floor loading requirements.
Install adequate floor support.
NOTICE: To ensure a successful installation, it is critical that bath be installed on a
level subfloor.
Verify the subfloor is level. Adjust for level, if necessary.
Framing
CAUTION: Risk of property damage. Do not support the bath by the rim. The
bath must be supported by the leveling blocks only or bath base, depending upon
your bath model.
NOTICE: The bath must be installed into a corner.
NOTICE: For drop-in models: To ensure the bath does not rest on the rim, a 1/16" (2
mm) gap must exist between the framing and the underside of the rim. When
constructing the framing, take into account the 1/16" (2 mm) gap and the thickness of
the finished wall/deck material.
Construct the framing according to the roughing-in information packed with the
bath. For drop-in models, ensure a 1/16" (2 mm) gap will exist between the
framing and the underside of the rim.
Plumbing
NOTE: For through-the-floor drain installations: A drain hole will need to be cut to
accommodate the drain connections. For above-the-floor drain installations: A hole
will not need to be cut.