Installing the Appliance

WARNING
Do not disassemble the top plate. Connected wire may become loose
and cause a malfunction.
1. Fasten the clamps to the main unit
(4 places on the front and rear).
- Put the Cushion UP underneath the main unit to act
as a buffer in order to prevent the countertop from
getting damaged.
- Match the clamp grips with the holes on the sides of
the main unit, then slide the clamp from the right to
the left to fasten them to the main unit.
2. Embed the main unit in the countertop cutout
while keeping it is as level as possible.
- Do not drop the unit on the countertop.
- Press down on top of the main unit to make sure
that the frame solidly rests on the countertop.
- Make sure that the spaces between the
countertop and the under surface of the top
frame are even in the front, rear, left and right.
Correct
Incorrect
3. Connect the power cord
See page 13.
14
Cushion UP
CAUTION
If the cabinet does not have an
opening in the front, the wiring needs
to be connected before the main unit
is embedded into the countertop.

Post-installation Checklist

Upon completing installation, check and mark off the following items.
Checklist
Appearance
- Does the appliance not look like it is tilted to the front,
rear, left or right?
- Is the frame not lifted up?
- Is the top plate clean?
Electrical
- Is the power supply a single-phase (220-240 V ~), or a
work
three-phase (380-415 V 2N~)?
- Has the earth been installed?
- Has the earth leakage circuit breaker been installed?
Electrical
1. Touch
to turn on the main power.
testing
- Does the main power light light up?
2. Touch the following keys to check function of each
IH heater:
- Left front heater
- Left rear heater
- Right front heater
- Right rear heater
- Make sure to turn off each IH heater and the main power switch after performing
electrical testing.
- Hand the Operating Instructions, Installation Instructions, and Guarantee Certificate to
the customer.
I hereby certify that installation has been completed.
Checked
Does "7" (heat
level display)
flash?
Signature of installer