Installation
To mount the crane boom to the forklift truck, position the lift
plate ① of the forklift truck under the upper fastening claws
② of the crane boom and then attach the lower fastening
claws ③ to the lift plate ① using the attached fastening
screws.
Attention: Observe the maximum permissible torque of
the fastening screws!
When mounting the crane boom, make sure that it is
positioned (as far as possible) centrally on the lifting plate ①
and that the shift protection ④ is used in the next possible
groove ⑤ on the lifting plate ①.
⑤
4.1.8
Load centre of gravity
•
When dimensioning the forklift truck, one expects that in normal driving operation the
suspension point is fully retracted and thus there is only a small load centre distance.
•
When using attachments, especially when using a distance adjustment VA, the distance of the
load centre is increasing, whereby the carrying capacity / working load limit of the fork lift
truck is reduced.
•
Only when the load is lifted ~10 cm (~ 4") above the storage area (e.g. lorry bed) and only
when the forklift stands still, it is allowed to move the mount point forward hydraulical, to put
down the gripping good. If this is not done, there is a risk of the forklift truck tipping over and
causing an ACCIDENT OR DEATH!
•
After putting down the gripping good, the moint point (the distance adjustment VA) has to be
retracted immediately.
57300001
①
16 / 23
②
③
GB