Step 1: Disassemble Eyewash
1. If the tank is pressurized, relieve the tank pressure by pulling up on the
relief tank tab in the center of the cover until the pressure gauge reads
"0."
IMPORTANT: DO NOT open the cover or remove the eyewash yoke
assembly until the pressure gauge reads "0."
2. Empty the tank of any water.
3. Disconnect and remove the old eyewash yoke (and old heater belt
and jacket, if previously installed). Inspect the tank fitting to ensure it is
clean and undamaged.
Step 2: Install Eyewash
1. Remove the plastic dust plug from the bottom of the yoke assembly and
discard. Attach the eyewash yoke assembly to the tank (see page 6).
IMPORTANT: DO NOT exceed the max. torque of 150 in-lbs. when
connecting the eyewash to the tank outlet.
Step 3: Install Heater Jacket
1.
Secure the pipe insulation and jacket to the eyewash yoke assembly.
2. Wrap the belt around the tank four inches from the bottom of the tank.
NOTE: For ease of assembly, line up the power cord from the heater pad
directly below the eyewash yoke assembly. Make sure the heater belt and
tank are clean and free of debris, then secure the belt to the tank.
3. Connect the heat trace cable to the junction box.
4. Slide the jacket up the outside of the tank.
NOTE: For ease of assembly, line up the pocket on the jacket, just to the
side of the eyewash yoke, away from the retaining spring on the heater pad.
5. Place the junction box in the pocket on the inside of the jacket. Route
the power cord out of the bottom of the hook-and-loop slot in the jacket.
6. Pull the drawstring tight at the top of the jacket.
Step 4: Fill tank and pressurize
IMPORTANT: DO NOT open the cover until the pressure gauge reads
"0."
1. Open the tank by pulling up on the wire handle located on top of the
Quicklock cover. Push down, rotate and remove. Fill the container with
4 gallons of potable water. Replace the cover.
3. After filling the tank with water and before pressurizing the unit, cycle
the valve from the closed to open and back to closed. Pressurize
the tank to 90 PSI by applying air pressure to the tank valve located
beneath the pressure gauge.
NOTE: Relief valve is designed to automatically vent at 100-130 psi to prevent
the tank from overpressurizing.
Step 5: Flush tank
1.
Discharge the water through the eyewash for at least five minutes to
flush the system.
2. Refill the tank and pressurize as explained in Step 4 outlined above.
NOTE: Let unit stand for one hour. If there is a noticeable pressure drop,
repressurize and let stand for one hour. If problems persist, consult the
Troubleshooting guide found on page 5.
NOTE: This unit will provide at least 7 minutes of cleansing action. Take
the injured person immediately to a normal emergency station for additional
cleansing and treatment.
3. Inspect the electrical components for any visible damage or fraying.
Plug the heater jacket's electrical cord into an appropriate electrical
outlet in accordance with state and local codes.
4
6/9/09
35
7
"
8
(911mm)
25¼"
(641mm)
27¾"
(705mm)
4"
(102mm)
Bradley Corporation • 215-321A Rev. U; ECM 08-539
Installation
10"
(254mm)
6"
(152mm)
Heat Trace
Cable
Junction
Box
Heater
Jacket
Heater Belt

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

S19-671hr

Table des Matières