unGer HYDRO POWER ULTRA UHP01 Mode D'emploi page 7

Table des Matières

Publicité

Les langues disponibles

Les langues disponibles

Installation & Operation
4. Installation and Operation
4.1 New Machine Setup
• Unpack unit: Inspect HydroPower Ultra unit and all components. Read warnings and
operating instructions.
• Inspection & Scope of Delivery: Refer to illustration; perform visual inspection and take
inventory of the following items that should be shipped with the system, then test system
for functionality:
• TDS Meter (powers on/off)
• FastLock lever (yellow) – depress lever, rotate in counter-clockwise direction and
remove top cap assembly.
• Ultra Resin Packs installed in unit.
- UHPR1 - One Green Pack
- UHPR2 - Three Green Packs
- UHPR3 - One Green & Two Red Packs
• Connection fittings installed in unit.
• Cart, wheels and tank clamp system (if purchased with cart).
• Water supply connection
• Inflowing water temperature max. 86°F
• Temperature on site 41°F to 104°F; and not in the immediate vicinity of heat sources
or in direct sunlight.

Publicité

Table des Matières
loading

Ce manuel est également adapté pour:

Hydro power ultra uhp3c

Table des Matières