2. Attach the trunk cable to the vertical cable mesh using velcro tie wraps (Figure 20).
Figure 20
3. Organize and group the fiber trunks in bundles as they will be connected at each Deck.
a. Positioning and routing cables that enter the frame entrance first will provide the best
bend radius control and utilization of the frame entrance point. (see figures X.X and X.X)
4. Mount each deck group into the cable clamp by removing the required rubber grommet rings.
a. Secure each trunk at the heat shrink as shown in Figure 21.
b. Secure the clamp by tightening the wing nut (Do not over-tighten or change the physical
characteristics of the cable jacket).
Figure 21
5. Mount the cable clamp to the Frame by inserting the clamp base at the desired location and
sliding until the mounting pin engages the hole (Figure 22).
DI-000-F3168-20B
Leviton HDF3168 Fiber Distribution System User Guide
Secure Velcro tie
wraps to the vertical
cable mesh at the
available lance points
28